Downtown road construction wraps up for winter

It started late and not as much got done as planned, but construction downtown has finished for the winter. Connor Coney with the city says they were hurt by harsh weather but were able to get a large chuck of the first phase finished.

That includes new sanitary, storm and sewer lines along 101st Street from behind Revolution Place to north of 100th Avenue. The waterline connection to the area was also replaced. Crews were able to pave and do curbs along that stretch, along the sidewalks between 99th and 100th Avenue are only temporary and will be replaced next spring.

Once the weather allows again, workers will continue north to the alley just past 102nd Avenue. They’ll then get started on the second phase, which will be on 101st Avenue from the Golden Age Centre to 100th Street.

Erica Fisher
Erica Fisherhttp://Erica
Content Manager/Afternoon Host
- Advertisement -

Related Articles

- Advertisement -

Latest News

Spirit River RCMP investigating aggravated assault, seek dashcam footage

Spirit River RCMP are asking the community for dashcam footage after a man was seen bloodied walking near Highway 2, in relation to an aggravated assault.

Local company fined more than $200K following fatal incident in 2022

North West Crane Enterprises Ltd is facing a $210,000 fine, after a fatal workplace incident involving a worker on a construction site near Clairmont in August of 2022.

AHS warns of possible measles exposure locations in Grande Prairie, Spirit River, Fairview

A confirmed measles case has prompted exposure warnings in Grande Prairie, Spirit River, and Fairview.

Dignity Drive set to start on October 1st

The Dignity drive will be kicking off their month-long fundraiser on Wednesday October 1st.

Charlene Nelson set for mayoral election campaign

Charlene Nelson has announced her campaign for mayor.
- Advertisement -